@@ -67,12 +67,78 @@ The steps that are introduced by \ridm are covered in more detail.

\subsection{Feature Definition}
\label{sec:featuredefinition}
During the feature definition, the system will be split into features as to prepare for the rapid development cycle and the variable-detail approach.
The goal is to split the system in such way that the resulting features are as small as possible, but can still be implemented and tested individually.
During the feature definition, the system will be split into features as preparation for the rapid development cycle and the variable-detail approach.
The aim of the \ridm is to have short implementation cycles to have early testing feedback.
To achieve this, the features are as small as possible, but can still be implemented and tested individually.
Together with the definition of the features, the requirements are divided along the features as well.
The optimal strategy on splitting features and specifications is strongly dependent on the type of system.
Therefore, the best engineering judgement of the developer the best tool available.

Sometimes features are dependent on each other, the implementation of one feature influences another.
This dependency can occur in specifications, where strength of one feature dictates the maximum mass of another feature.
Such a dependency can work both ways and can be resolved by strengthening the one feature, or reduce the weight of the other feature.
Another type of dependency is when the implementation influences other features.
In this case, if the implementation of one feature changes, it requires a change in the other features.
An example of this is a robot arm, where the type of actuation strongly influences the end-effector.
When the robot arm approaches an item horizontally, the end-effector will be different than approaching the item vertically.

Due to these dependencies it is possible that the division of requirements changes, because the result of the implemented feature was not as expected.
This is not directly a problem, but a good administration of the requirements makes an update of the requirements easier.

\subsection{Feature Selection}
\label{sec:feature_selection}
The rapid development cycle does not specify which feature should be implemented first, even though the order of implementation does change the feasibility of the complete development.
An example that shows the importance of the order of features is the development of a car.
To have a critical damped suspension in a car, the weight distribution of the car must be known.
If the suspension of the car is designed before all the features that determine the weight distribution, it is likely that the suspension design is not up to specifications.
Resulting in a redesign of the suspension feature and thus increasing the overall development cost.
This example is caused by the dependency between different features.

For the design plan, the order of implementation of features will be determined by the following rules:
\begin{enumerate}
\item Features that are dependencies of others must be implemented first.
\item Features that complete more system test than other features when implemented have priority.
\item Features with the higher \emph{risk per time} score than other features have priority.
\end{enumerate}
The risk per time score for third rule is calculated by dividing the risk score with the time score.
The goal of this score is to eliminate as much risk as possible in the least amount of time.
It seems logic to always implement the highest risk feature first, but it is possible that within that feature multiple lower risk features can be finished.
This is visible in \autoref{tab:feature_selection}: In a time span of 6 days it is possible to implement feature E or features A, C, and D.
The risk that is cleared by E is 45 \% which is significantly less than the combined 65 \% of A, C and D.
Due to the limited scope of this thesis, it is not possible to give a good metric for determining risk and time.
Nevertheless, it is strongly advised that the developer defines some metric that fits his project best.

\begin{marginfigure}
\centering
\includegraphics[width=2.9cm]{graphics/feature_dependency.pdf}
\caption{Dependency graph for features.}
\label{fig:feature_dependency}
\end{marginfigure}
\begin{table}[]
\caption{Comparison of features with their corresponding risk and time.
The last column is the risk value divided by the number of days.}
\label{tab:feature_selection}
\begin{tabular}{l|r|r|r|r|r|}
\cline{2-6}
& \multicolumn{1}{l|}{Dependees} & \multicolumn{1}{l|}{Tests} & \multicolumn{1}{l|}{Risk} & \multicolumn{1}{l|}{Time} & \multicolumn{1}{l|}{Risk per time} \\ \hline
\multicolumn{1}{|l|}{Feat. A} & 2 (2, 3) & 2 & 15 \% & 3 days & 5 \\ \hline
\multicolumn{1}{|l|}{Feat. B} & 0 & 3 & 40 \% & 5 days & 8 \\ \hline
\multicolumn{1}{|l|}{Feat. C} & 1 (5) & 5 & 25 \% & 2 days & 12.5 \\ \hline
\multicolumn{1}{|l|}{Feat. D} & 0 & 4 & 15 \% & 1 day & 15 \\ \hline
\multicolumn{1}{|l|}{Feat. E} & 0 & 4 & 45 \% & 6 days & 7.5 \\ \hline
\end{tabular}
\end{table}
Looking at an example of 5 features:
As seen in \autoref{fig:feature_dependency}, Features B and C are dependent on feature A.
Feature D does not have any dependency connections, and feature E is dependent on C.
Together with the information in \autoref{tab:feature_selection}, the order of implementation is:
\begin{description}
\item[Feature A:] has two features that are dependent on this feature, more than any other.
\item[Feature C:] has one feature that is dependent on this feature, most dependencies after A is implemented.
\item[Feature D:] has the same number of tests as E, but D has a significant higher risk per time score than E
\item[Feature E:] has the most number of tests.
\item[Feature B:] only one left to be implemented.
\end{description}